BPF configuration: parallel and dependent steps

$
0
0

Hi all,

 

I have a BPF of let say 5 steps regarding 5 input form.

 

step 1 is the main step and inputted by budget team.It is the rates input form.

step 2 is the sales volume step and depend on step 1 (like other steps) inputted by sales team.

step 3 is the sales discount step and depend on step 1 -2 inputted by budget team.

step 4 is the cost step depend on step 1-2 and can be performed regardless of step 3 and inputted by finance team.

step 5 is the distribution of costs to sales cube to see the profitableness and depend on step 1-2-4 .

 

As you see there are both parallel and related steps.Of course there are many other steps but they are similar so I summarized them as 5 steps.

Note that sales cube consists of sales  group and cost cube consists of cost center( candidates for drive dimension)

Let me depict the scheme  for that:

 

 

 

I could not achieve this by creating steps of openning criteria as "matched " or creating more than 1 template and instance. I want to know whether it is possible or there is a workaround.