Quantcast
Channel: SCN : Discussion List - SAP Planning and Consolidation, version for SAP NetWeaver
Viewing all articles
Browse latest Browse all 5414

Change Work Status for Several members at once

$
0
0

Hi Guru,

 

Based on documentation Work Status requires a minimum of 3 dimensions.

My needs are just 2 dimensions (Profit center Node and Version).

I was looking for a dimension rarely used in my model but all dimensions are used and have a significant amount of members. So I would probably add time dimension as the 3rd dimension.

Unfortunately, I noticed that I can't lock several months at once. I can select "include all descendants" for the first dimension of the work status, but not for the other two.

 

I feel quite surprise and in my case (where a version always consists of 24 months) it means that I would be asking key users to set the work status 24 times for a single Profit Center node (once for each month). It's rather cumbersome.

 

Is there no way to reduce the number of dimensions relevant for Work Status?

Is there no way to set the work status for a node of profit centers and several months just with a single work status action?

 

 

BPC NW 10 SP 5

EPM Add-in Patch 20

 

 

Thanks in advanced,

 

 

Alberto Sabate


Viewing all articles
Browse latest Browse all 5414

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>