Dear,
client is on SAP BPC NW 10 , SP12 .
They have two datamanager packages which execute a script logic, from within the currency conversion is called in both logics.
Both packages are scheduled to run in a process chain, using the ZUJD_TEST_PACKAGE program to execute the packages.
When the package is executed from the scheduled process chain, it gives an invalid error related to work status - but the user executing
the package should be able to change the data.
When the package is scheduled from BPC, it succeeds and data is changed. When the process chain is executed synchronously , the package also succeeds. It seem only to give the work status error when it is launched with a job.
Anyone encountered this issue ?