Unable to change work status in BPC 10 NW after patch upgrade from 12 to 20

$
0
0

Hi Folks,

 

Greetings!!

 

We have recently upgraded patch level of BPC 10 NW from SP12 to SP20. There are many issues and majority of them got resolved by self and with SAP intervention but one peculiar issue still exists in the system. Work status is behaving different now as compared to previous patch.

 

We have three work-status maintained in our project which are listed below.

 

1. Unlocked  - Owner

2. Submitted - Manager

3. Locked      - Manager

 

Two issues of work-status exists in the system:

 

  1. When we try to change Work Status in BPC it works fine till 2015.05 period for single entity but gives us an authorization issue after this period (E.g. 2015.07) in Consolidation Model. Screenshots attached for your reference .
  2. To unlock whole parent with dependents check in is not at all working for any period.

 

We patched Quality first before getting into production and setting are same as in Production and there is no scope of changes from BPC front end (admin) side as production is working as expected. I would like to know can we do something from BW end.

 

I hope experts here can help me out to get a resolution at the earliest.

 

Thanks in advance. Please revert for any further information.

 

Thanks and Regards,

Mahesh Reddy