Hi Experts,

 

We are working on BPC 10.1 NW, I am trying to change the work status in the consolidation monitor.

 

Three issues I am encountering are:

 

1. Work status when applied at entity level in the consolidation monitor, the pop says the work status is applied, but the status in the monitor does not change, while if I do the same from excel addin it applies the status changes in the consolidation monitor.

 

2. When I keep the cursor on the group  in the consolidation monitor and try to execute, the same does not work.

 

3. When the work status is applied in the excel add  by selecting the entity hierach, the status for all the entities changes to in consolidation monitor, but the groups still have no changes in the status.

 

 

Capture2.JPG

 

 

Please advice.


Regards,

Shilpa